Project Profiles
EnCana
Foster Creek SAGD facility, Cold Lake, Alberta
Packaged Wastewater Treatment
Capacity: 180 m3/day
Commissioned: January, 2002
Technical Parameters:
The treatment system was a packaged activated sludge treatment
system comprised of fine screening, flow equalization, extended
aeration activated sludge and tertiary filtration for treatment
of high strength domestic wastewater from a remote construction/operations
camp for a major oil sands development project. The system
was designed and constructed as a complete facility installed
on skids to allow for rapid installation and start-up of
the system. The treatment plant achieved discharge compliance
within 7 days of start-up and has never been out of compliance
with its discharge permit. Prior to the system being installed,
the client was required to truck the camp sewage to a municipal
sewage treatment facility at a cost of up to $3000/day.
Petro-Canada
Mackay River Oil Sands Project Fort McMurray Alberta
Packaged Wastewater Treatment
Capacity: 25 m3/day
Commissioned: November 2002
Technical Parameters:
The treatment system was a packaged activated sludge treatment
system comprised of fine screening, flow equalization, extended
aeration activated sludge and tertiary filtration for treatment
of high strength domestic wastewater from a remote construction/operations
camp for a major oil sands development project. The system
was designed and constructed as a complete facility installed
within two industrial trailer units to allow for rapid installation
and start-up of the system. The treatment plant achieved
discharge compliance within 7 days of start-up and has never
been out of compliance.
Petro-Canada/Akita,
Mackenzie Delta Drilling Program
Packaged Wastewater Treatment
Capacity: 20 m3/day
Commissioned: November 2002
Technical Parameters:
A physical/chemical treatment system was supplied to treat
high strength domestic wastewater from a remote drilling
camp in the Canadian arctic. The treatment system employed
a proprietary physical/chemical treatment process with sludge
dewatering and uv disinfection. The treatment plant was
the first system to meet the required standards for direct
discharge to the arctic tundra. No other system achieved
the required standard in the past 3 drilling seasons.
PTI
Group - CNRL North Helmut Operations Camp
Packaged Wastewater Treatment System
Capacity: 25 m3/day
Commissioned: November 2002
Technical Parameters
The treatment system was a packaged activated sludge treatment
system comprised of fine screening, flow equalization, extended
aeration activated sludge and tertiary filtration for treatment
of high strength domestic wastewater from a remote construction/operations
camp for a major oil sands development project. The system
was designed and constructed as a complete facility installed
within two industrial trailer units to allow for rapid installation
and start-up of the system. The treatment plant achieved
discharge compliance within 7 days of start-up and has never
been out of compliance.
Canadian
Forces Camp Julian, Afghanistan
Packaged Water Treatment System
Capacity: 350 m3/day
Commissioned: August 2003
Technical Parameters:
The system employed nanofiltration technology to remove
total dissolved solids as well as provide 6-log removal
of Cryptosporidium, Giardia, and bacterial contamination.
The system also included ultraviolet disinfection and addition
of a chlorine residual. Water distribution pumps and pressure
system were also supplied. The complete nanofiltration water
treatment system was skid mounted and designed to be transported
within a C130 cargo plane. The system was completed and
ready to deploy to the Afghanistan Theatre within 30 days
of receipt of order.
Click any image to enlarge